provide details of the nature of work undertaken (proposed to be undertaken) at each location, and a detailed breakdown of costs at each playground;

(3) In relation to Packages 4 and 5, please identify the nature of the work proposed to be conducted at each location selected, including a timeframe for construction; estimated breakdown of expenditure;

(4) In relation to Package 6, why is this package not programmed for completion until "mid to late 2003/04 financial year";

(5) Is it proposed for playgrounds included in Package 6 to be revised at a future date or is this package already final;

(6) Are there plans for further playgrounds to be included in funding allocated in Budget 2003/04 in a supplementary safety program, and, if so when can details of playgrounds not included in Packages 1 to 6 be expected to be announced.

Mr Wood

: The answer to the member's questions is as follows:

(1) All playgrounds in Package 2 have been completed except Chippendale Circuit, Theodore. The delay for completion of this playground is due to a decision to carry out more extensive works than was originally planned for this playground. The expected completion will be mid August 2003.


The construction tender for package 3 has been awarded. Completion of Package 3 is expected in early to mid September 2003. Completion of Package 3 has been delayed due to longer than anticipated manufacture time for play equipment.

(2) The work undertaken for playgrounds in Package 2 is as follows:

Playground

Works Completed

Works Proposed

Bettington Circuit, Charnwood

replace swing, softfall, seat and concrete edging

Bingley Crescent, Fraser

replace swings

recap retaining wall

Pulleine Street, Macgregor

replace swings and softfall

repair seat and edging

Woolner Crescent, Hawker

replace swings, retaining wall, softfall and seat

Chippindall Circuit, Theodore

replace play equipment

replace softfall

replace seat

The works proposed for playgrounds in Package 3 is as follows:

Playground

Works Completed

Works Proposed

Alberga Street, Kaleen

replace play equipment

replace softfall

increase softfall area

Burkitt Street, Page

replace play equipment

replace softfall

increase softfall area