Next page . . . . Previous page . . . . Speeches . . . . Contents . . . . Debates(HTML) . . . .
Legislative Assembly for the ACT: 2003 Week 7 Hansard (26 June) . . Page.. 2716 ..
(5) Are there any losers in changing the details of this project, if so, who.
Mr Wood
: The answer to the member's questions is as follows:(1) The Department of Urban Services, Capital Works Program, December Quarterly Report had inadvertently named the Libraries Improvement Program as the Civic Library Strategy. This was rectified in the March Quarterly Report.
(2) By the end of the March Quarter we were significantly advanced in delivering the Libraries Improvement Program with works in progress in the following locations:
Belconnen
- Cooling tower controls system and support
- Internal lighting
- Fire and lift services
Woden
- Air conditioning
- Mechanical, fire and lift services
Civic
- Replacement front door operator mechanism
Tuggeranong
- Air conditioning management system and control work
- Fire services
Griffith
- Heating, mechanical and fire systems work
- Roofing and guttering
(3) The main aim of the program is to provide funding to address items identified in Condition Audits and include OH&S, fire, air conditioning and disabled access in various libraries.
(4) The aim of the program has not changed from that originally stated in the Budget Papers - refer page 190 of revised BP4, 2002-03 - which clearly states the $500,000 approved funding is for the Libraries Improvement Program.
(5) There has been no change to the details of the original program.
Playground Safety program
(Question No 800)
Mrs Burke asked the Minister for Urban Services, upon notice:
In relation to the Playground Safety Upgrade Program, further to your reply to Questions on notice numbers 577 and 683.
(1) Have all playgrounds identified for construction work in Packages 2 and 3 now been completed. If not, please identify which playgrounds remain unfinished, what stage each playground is at, when it can be expected for completion of work, and why completion has been delayed (in each case);
(2) In relation to all playgrounds in Packages 2 and 3, whether or not completed, please
Next page . . . . Previous page . . . . Speeches . . . . Contents . . . . Debates(HTML) . . . .