Commonwealth Grant Details |
Funding/expenditure to date |
Outcomes/Key Performance Indicators (KPIs)/Reporting |
Transport Canberra and City Services Directorate (TCCS) | ||
Blackspots Program |
The Commonwealth provided funding of: • $2.3 million in 2015-16 • $1.4 million in 2016-17; and • $1.8 million in 2017-18 Of this funding, $6.4 million was expended over the period 2015-16 to 2017-18. Note: Expenditure exceeds funding due to re-profiling of funding provided prior to 2015-16. |
Acquittal of all expenditure under the grant program and evidence the funds have been spent appropriately. |
Interstate Road Transport |
The Commonwealth provided funding of: • $0.4 million in 2015-16; • $0.3 million in 2016-17; and • $0.4 million in 2017-18 Of this funding, $1.1 million was expended during the period 2015-16 to 2017-18. |
Acquittal of all expenditure under the grant program and evidence the funds have been spent appropriately. |
National Projects: National Network Maintenance |
The Commonwealth provided $2.2 million of funding over the period 2015-16 to 2017-18, with $1.9 million of this expended over the same period. |
Acquittal of all expenditure under the grant program and evidence the funds have been spent appropriately. |
National Projects: Majura Parkway |
The Commonwealth provided funding of $6.9 million in 2015—16, with $32.3 million expended on this project from 2015-16 to 2017-18. Note: Expenditure exceeds funding due to re-profiling of Commonwealth funding provided prior to 2015-16. |
Acquittal of all expenditure under the grant program and evidence the funds have been spent appropriately. |
National Projects: Bridges Renewal Program – Round 1 |
The Commonwealth provided $492,000 of funding in 2015-16, all of which has been expended. |
Acquittal of all expenditure under the grant program and evidence the funds have been spent appropriately. |
National Projects: Bridges Renewal Program – Round 2 |
Funding of $1.0 million was provided for this agreement in 2016-17, all of which has been expended. |
Acquittal of all expenditure under the grant program and evidence the funds have been spent appropriately. |
National Projects: Off Network – Roads – Technology – ACT Travel Time Information |
The Commonwealth provided $0.3 million over two years (2015 16 and 2016-17). All of this funding was expended over the period 2015 16 to 2017-18. |
Acquittal of all expenditure under the grant program and evidence the funds have been spent appropriately. |
National Projects: National Highway Upgrade Program – Federal Highway Truck Lay-bys |
The Commonwealth provided funding of $3.2 million for this project in 2015-16, all of which has been expended. |
Acquittal of all expenditure under the grant program and evidence the funds have been spent appropriately. |