(2) What was the average time taken by ACTPLA or its predecessors for approval of a (a) non single residential and (b) commercial development each year from 1995 to 2005 inclusive, not including those which were subject to call in powers being exercised.

Mr Corbell: The answer to the member’s question is as follows:

(1)

Development applications received (not including those which were subject to call in powers being exercised):

Year

(a) single residential lodgements

(b) and (c) non single residential & commercial lodgements*

1995

4122

1006

1996

3747

874

1997

4107

827

1998

4368

959

1999

4279

981

2000

3596

1013

2001

4139

930

2002

5069

962

2003

4947

776

2004

4228

831

2005

3988

896

* Unable to split data into non single residential and commercial as data not collected in this way

(2)

Average time for approval (business days) - not including those which were subject to call in powers being exercised:

Year

(a) and (b) non single residential and commercial *

1995

71

1996

45

1997

35

1998

41

1999

34

2000

39

2001

30

2002

30

2003

33

2004

35

2005

29

* Unable to split data into non single residential and commercial as data not collected in this way