1. | 2. | 3. | 4. |
Name of inquiry, | Cost to date | Further advice on the cost of the project to the agency | Terms of reference or guidelines |
review, committee or | and total cost | ||
taskforce | to Government | ||
A Methodology to | $22437 | Nil | Identify outputs which reflect the funding programs policy objectives across funded services and measures which permit comparison of like outputs between services and cost comparison. Intangible outputs, that is those which are not readily measurable, should be identified. Where outputs can be measured, use appropriate output based funding techniques identified by Johnston Policy Futures (JPF) to develop a range of standard price formulas for application across community services Where outputs cannot be readily measured, use appropriate input based funding techniques identified by JPF to develop a range of standard price formulas for application across community services |
Determine Standardised | |||
Prices for Community | |||
Services Provided by | |||
Non-Government | |||
Organisations. | |||
Development of Pilot | The total cost of the project to date is $79,335. CMD contributed $20,000, Health $15,000, DECS $29,865 and DHCS $14,470. | Nil | Develop generic standards which can be customised for use by a range of services funded by ACT Department of Education and Community Services and ACT Department of Health and Community Care that do not have standards against which to monitor service provision. |
Generic Service | |||
Standards for | |||
Community Services | |||
The project commenced | |||
on 19 December 2000. | |||