Page 1477 - Week 05 - Thursday, 13 May 1993
Next page . . . . Previous page . . . . Contents . . . . Debates(HTML) . . . . PDF . . . .
MINISTER FOR EDUCATION AND TRAINING
LEGISLATIVE ASSEMBLY QUESTION
QUESTION NO 608
Conder Primary School
MR CORNWELL - asked the Minister for Education and Training on notice on 23 March 1993:
(1) Is the capacity of Conder Primary School, without demountables, the 460 students shown in 1992-93 Capital Works Budget Paper 4 (p.63) or 592 students as advised by the Education Projects Section of the Department A Urban Services to the Assemblys Standing Committee on Planning, Development and Infrastructure.
(2) What is the estimated cost of building Conder Primary
School - (a) $7 .1 million (Budget Paper 4) or
(b) $6.85 million (Education Projects Sections).
MR WOOD - the answer to Mr Cornwells question: is:
(1) Conder Primary School is to have a permanent capacity for 460 students. This is the standard provision for new primary schools, whereby 16 classrooms are provided for class sizes of 30 in Years 1 to 6, and 25 in kindergarten.
(2) Previous figures were estimated costs. The current contract cost of the project is $6,314,000.
Next page . . . . Previous page . . . . Contents . . . . Debates(HTML) . . . . PDF . . . .