Cycle Network Improvements and (c) Footpath and Cycleway upgrades – Community Paths, can the Minister provide a list of works funded under these initiatives, including status, and estimated completion date for uncompleted works.

Mr Steel: The answer to the member’s question is as follows:

Status and expected completion dates for the projects are listed below for (a) Walking – Community Paths, (b) Cycling – Cycle Network Improvements and (c) Footpath and Cycleway upgrades – Community Paths

Initiative

Status

Revised Estimated Completion

Capital works

(a) Walking - Community Paths

Package 1 – Design Stage

• Giralang: Primary School to underpass

• Kaleen: Baldwin Dr to Tyrell Cct

• Narrabundah: Kootara Cr to Wambool St

• Torrens: Batchelor St to trunk path

• Hackett: Bus Stop 3196 to Antill St service road

• Lyons: Launceston St from underpass to Burnie St

• Gungahlin: The Valley Ave at Hinder St

• Turner: McCaughey St from Masson St to Barry Dr

• Barton: Darling St

• Barton: New South Wales Crescent at Telopea Park

• Ngunnawal: Intersection of Horse Park Dr and Gungahlin Dr

• Kingston: Currie Crescent at childcare centre

Late 2020

• Downer: Swinden St ramp

• Florey: Bus stop 5003 on Southern Cross Dr to existing path network

Package 2 – Construction tender stage

• Wanniassa: Hindmarsh Dr to Arawang Primary School

• Monash: Cockroft Ave Bus Stop 1441 to shops

• Greenway: Soward Way northside to car parks

• Greenway: Soward Way southside to Archery club

• Bonython: Barr Smith Ave at Derrington Cr

(b) Cycling - Cycle network Improvements

Part 1 Priority Crossings – In construction

• O’Connor: Hovea St wombat crossing

• O’Connor: Boronia Dr path upgrade

Late 2020

• O’Connor: Dryandra St wombat crossing

• O’Connor: Kunzea St zebra crossing

• Lyneham: Wattle St path improvements

• Turner: McCaughey St/Masson St wombat crossing

• Kaleen: Cossington Smith Cr wombat crossing

• Yarralumla: Weston St wombat crossing

• Deakin: Yarra Glen drainage improvements

Part 2 Wayfinding

PCR branding and MCR signage - In construction stage

• PCR C1 City to Gungahlin

• PCR C4 City to Tuggeranong

• PCR C5 Belconnen to Tuggeranong

• PCR C6 ANU to Dickson

PCR branding and MCR signage (Design Only) – design stage

• PCR C3 City to Belconnen

• PCR C7 Belconnen to Gungahlin

• PCR C8 City Loop