(c) The original budget for construction works associated with the electrical main switchboard board project was $14.0 million (incl. GST).

(d) The Shaw Building Group contract is currently $41.9m (incl. GST) which differs from the original budget for the following reason:

The original scope of work was to replace ageing Building 2 and 12 switchboards and associated electrical cabling that were identified as high or extreme risk. The difference between the original budget and the current contract amount reflects the increase in project scope linked to the following areas:

to address significant associated risks with ageing infrastructure that were not able to be quantified prior to commencement of the construction works.

to address the risk of failure during the works from disturbing the ageing electrical infrastructure including the replacement of new submain cables and reticulation infrastructure, business continuity switchboards, submain upgrade and hire of additional backup generators to reduce the risk of further unplanned outages until the project was completed.

to provide an increased level of electrical supply redundancy to support Canberra Hospital’s status as the only Tertiary level hospital in the region requiring continuity of electrical service supply at all times.

(e) Design (to the extent specified) and Construction of Canberra Hospital Main Electrical Switchboards Replacement

(5) Details of notifiable invoices for “UCPH Design Specification and Documentation” between go live (July 2018) and 31 January 2019 are:

July 2018

Nil

August 2018

Progress claim on post completion changes and the supply and installation of a Car Park Guidance System

Temporary traffic management measures during construction of the Multi Storey Car Park

September 2018

Progress claim on post completion changes

Supply and installation of additional storage and changes to the Clean Utility Rooms

Progress claim for the supply and installation of a Car Park Guidance System

Supply and installation of building identification signage

October 2018

Nil

November 2018

Progress claim on post completion changes and the supply and installation of a Car Park Guidance System

Progress claim for the fit out of the Medical Imaging Room