The primary objective is to deliver a large, regular preventive resurfacing program using relatively low-cost treatments to maximise the effect of the available budget. Examples of preventative treatments include chip seal and microsurfacing. This approach aims to prevent structural damage to the road and minimise the requirement for relatively high cost corrective treatments.

Annual reseal programs are required to be delivered in the warmer months between October and April each year.

(2) Between 18 and 23 January 2018 the following streets in Ainslie were resealed.

Baker Street;

Campbell Street;

Leslie Street;

Quick Street;

Sutter Street;

Campbell Street Service Road;

Suttor Street Service Road 1; and

Suttor Street Service Road 2.

Where necessary these streets were patched with asphalt in mid-2017 in preparation for the resurfacing. Progress payments total $138,500 (GST exclusive) in relation to resealing in Ainslie since 1 July 2017. There will be future payments on final completion and acceptance of the work.

(3) Records are kept by area not by length. 21,809 square metres of road have been resealed in Ainslie since 1 July 2017.

(4) Resealing is delivered under a contract to provide a complete service. The component costs are not a reporting requirement of the contractor.

(5) The resealing contract was procured by open public tender.

(6) The resealing contract is procured by open public tender.

(7) Downer is currently engaged to undertake resealing, the contract expires at the end of June 2021.

Contract Number:

2016.27122.111

Contract title:

Resealing of ACT Roads 2016-2021

Value of Contract:

$45,436,329.32

(8) Based on condition assessments, as outlined at 1) above, the roads in Ainslie were prioritised for resealing to prevent water penetration into ageing road surfaces.

(9) No.

(10) Number of requests for road maintenance received through Fix My Street (categories included potholes, roads).

Year

Total

2015

0

2016

19

2017

18

2018

2