2011-12

10 November 2011

ACTEW Letter to VS providing first quarter report against Statement of Corporate Intent (SCI). Key items included:

- Progress on ECD and rectification of the geological fault

- Further work to address recommendations in the Canberra Sewerage Strategy 2010-2060 Future Sewerage Options Report. Strategic plan developed for the Fyshwick sewerage plant.

- Financial Performance

11 November 2011

ACTEW letter to VS advising of key matters discussed at 9 November 2011 Board meeting including:

- Transact

- Reintegration of the Water business

- MWSP

20 December 2011

MD wrote to the VS including advice that ECD project schedule and budget under pressure.

21 December 2011

ACTEW letter to VS providing quarterly report September 2011 to November 2011 against the SCI. Key items included:

- Work on the ECD interrupted due to adverse weather conditions

- Compliance issues and prohibition notices raised by Worksafe have been addressed and progressed

- Financial Performance

3 February 2012

MD wrote to Chief Minister about disruptions to ECD construction.

6 February 2012

ACTEW letter to VS providing second quarter report 2011-12 against the SCI

8 February 2012

ACTEW letter to VS advising of key matters discussed at 1 February 2012 Board Meeting including:

- MWSP update

- Reintegration of the Water business

- Review of water restrictions

9 February 2012

ACTEW letter to Deputy Chief Minister regarding ACTEW’s involvement in the Government Business Development Strategy as advised by the DCM.

4 March 2012

ACTEW Board meeting on 4 March 2012 resolved to provide weekly briefs to the VS on the ECD.

5 March 2012

ACTEW meeting with VS to discuss ECD project and flooding implications.

9 March 2012

MD ACTEW wrote to VS with a summary of matters discussed at the 4 March Meeting including:

- ECD

- Murrumbidgee to Googong Pipeline

- Reintegration of Water business

- Proposed new Information Management System

9 March 2012

First weekly ECD report to Board and VS including impact of water continuing to flood ECD construction work.