(15) (a) These contracts were to remove and remediate underground storage tanks at Wanniassa Senior School and Wanniassa Junior School.

(b) The payments were for tank excavation at each location.

(16) (a) The contract was for carpet replacement due to leaking heaters and roof at Melrose High School.

(b) They payment was for carpet replacement.

(17) (a) The contract for this payment was for Joint Facility Canteen upgrade for use by the Gold Creek Junior School and the Holy Spirit Primary School to improve the safety, functionality and aesthetics of the joint facility.

(b) The payment was for refurbishment works, including replacement of existing stainless steel benches, new cupboards, painting, and a new access door for deliveries, to accord with health regulations.

(c) The facility upgrade was at the Gold Creek Junior School and the Holy Spirit Primary School (shared campus).

Government—expenditure
(Question No 109)

Mr Wall asked the Treasurer, upon notice, on 17 February 2017:

(1) In relation to payments made from the ACT Government on 2 June 2016 to Deakin University, (a) who attended the forum and (b) how were the participants selected.

(2) In relation to payments made from the ACT Government on 5 June 2016 to Woods Furniture Pty Ltd, (a) what was the scope of the contract, (b) what goods or services were delivered and (c) at what school was the upgrade for.

(3) In relation to payments made from the ACT Government on 7 June 2016 to Robson Environmental, what (a) was the scope of the contract and (b) goods or services were delivered.

(4) In relation to payments made from the ACT Government on 7 June 2016 to Complex Civil Pty Ltd, what capital upgrades were carried out.

(5) In relation to payments made from the ACT Government on 7 June 2016 to SMI Group Pty Ltd, what capital upgrades were carried out for each payment.

(6) In relation to payments made from the ACT Government on 9 June 2016 to Tri-Delt Pty T/A Quay Building Group, what (a) was the scope of the contract and (b) goods or services were delivered.

(7) In relation to payments made from the ACT Government on 13 June 2016 to Royal Life Saving Society Australia ACT Branch Inc, what schools participated in the program.

(8) In relation to payments made from the ACT Government on 14 June 2016 to AGH Demolition & Asbestos Removal Pty Ltd, what (a) was the scope of the contract and (b) goods or services were delivered.