(2) (a) This invoice was for brushing down trucks, and supervision and advice for removal of contaminated material as required.
(b) The services were delivered on 7, 11 and 20 November 2015.
(c) The services were an urgent requirement due to fire and were acquired through a work order following direct sourcing (hourly rates).
(3) (a) This payment was for supervision of contaminated waste removal services.
(b) The services were provided on 11 and 27 November 2015.
(c) The services were an urgent requirement due to fire and were acquired through a work order following direct sourcing (hourly rates).
(4) This consultancy was for the National Partnership Agreement on Empowering Local Decisions.
(5) (a) This payment was for the removal of contaminated waste.
(b) The services were provided on 4 and 8 November 2015.
(c) Dale & Hitchcock Civil Engineering & Landscaping was selected from a panel of contractors established following a public tender.
(6) (a) This payment was for a clean-up after a fire at the Parkwood Recycling Estate.
(b) The services were provided on 12 November 2015.
(c) The supplier was selected from a panel of contractors established following a public tender.
(7) (a) This payment was for clean-up and disposal of rubbish from the Parkwood Recycling Estate.
(b) The services were delivered on 27 and 29 November 2015.
(c) Goldsmiths Civil and Environment retain contract for material movement within Belconnen Waste Resource Centre following a public tender.
(8) (a) This payment was for internal audit services.
(b) The purpose of the services was to provide two internal compliance audits.
(c) The two internal compliance audits covered compliance with record keeping processes for cabinet documents; and grants and contract expenditure forecasting.
(9) (a) This payment was for clean-up after a fire at the Parkwood Recycling Estate.
(b) The services were provided on 13 and 15 November 2015.
(c) The supplier was selected from a panel of contractors established following a public tender.
(10) (a) This payment was for supervision and advice for the removal of asbestos from the Parkwood Recycling Estate.
(b) The services were delivered on 21 November and 4 December 2015.