Page 1080 - Week 03 - Thursday, 23 March 2017

Next page . . . . Previous page . . . . Speeches . . . . Contents . . . . Debates(HTML) . . . . PDF . . . . Video


(1) Can the Minister provide a list of the master plans that have not yet been finalised and when they are expected to be finalised.

(2) Can the Minister provide a list of the master plans that have been incorporated into the Territory Plan and indicate whether the master plans have been fully or partially incorporated.

Mr Gentleman: The answer to the member’s question is as follows:

(1) Master Plans currently in progress include:

• Kippax Centre Group Master Plan – anticipated to be finalised in 2017/18.

• Curtin Group Centre Master Plan – anticipated to be finalised in 2017/18.

• Tharwa Village Plan – anticipated to the finalised in 2017/18.

(2) Master Plans incorporated in the Territory Plan include:

• Dickson Group Centre Master Plan – May 2011 (Territory Plan variation 311 - June 2013).

• Kingston Group Centre Master Plan –June 2011 (Territory Plan variation 314 - May 2014).

• Kambah Group Centre Master Plan - July 2012 (Territory Plan Variation 317 - 30 May 2014).

• Tuggeranong Town Centre Master Plan – September 2012 (Territory Plan variation 318 - October 2014).

• Erindale Group Centre Master Plan - September 2012 (Territory Plan variation 320 - November 2015).

• Pialligo Rural Village Master Plan - November 2013 (Territory Plan variation 321 - August 2015).

Completed Master Plans to be incorporated in the Territory Plan include:

• Weston Group Centre Master Plan- December 2014.

o A review of the Weston draft Territory Plan variation 329 is currently on hold while a contamination study is completed, as requested by the EPA.

• Oaks Estate Master Plan - December 2014.

o A review of the Oaks Estate draft Territory Plan variation 328 is currently on hold while the Heritage Council considers the heritage nominations for Oaks Estate.

• Woden Town Centre and Mawson Group Centre Master Plans - November 2015. (Prepared simultaneously to align the relationships between metropolitan transport, land use and infrastructure).

o The draft Territory Plan variations including replacement precinct codes for the centres are being finalised and will be issued shortly for community engagement following Government consideration.

• Belconnen Town Centre Master Plan - September 2016. The draft Territory Plan variation including a replacement precinct code for the centre is currently being finalised and will be issued for community engagement following Government consideration.


Next page . . . . Previous page . . . . Speeches . . . . Contents . . . . Debates(HTML) . . . . PDF . . . . Video