projects, how many projects have been agreed (a) to be completed and have subsequently been completed, (b) to be completed but have not been completed and (c) to not be completed.

Ms Fitzharris: The answer to the member’s question is as follows:

(1) Works being delivered in the 2016-17 Capital Works construction program are as follows:

a)

Phillip - Butters Drive.

b)

Forrest - Canberra Avenue median.

c)

Kambah - Athllon Drive.

d)

Belconnen - College St.

e)

Deakin - Gawler Crescent.

f)

Holt - Flack Street.

g)

Florey - John Cleland Crescent.

h)

Acton - Hales Street.

i)

Acton - Off-Lady Denman Drive.

j)

Bruce - Thynne Street.

k)

Kingston - Wentworth Avenue.

l)

Turner and O’Connor – Sullivans Creek Shared Path.

(2) The list of Community Path priorities is available on the TCCS website:

http://www.tccs.act.gov.au/roads-paths/cycling/community-path-warrant-list

An updated listing of priority projects is provided as Attachment A.

(3) Works being delivered in the 2016-17 Capital Works design and construction program are:

a)

Gungahlin - Anthony Rolfe Avenue at Moonlight Avenue and

De Bortoli Street.

b)

Gungahlin - Ernest Cavanagh Street and Fussell Lane.

c)

Forrest - Tasmania Circle.

d)

Woden Town Centre – Easty Street.

e)

Woden Town Centre – Matilda Street.

(4) Works being delivered in the 2016-17 Capital Works design program are:

a)

Fyshwick – Canberra Avenue.

b)

Calwell – Were Street.

c)

Mitchell - Well Station Drive.

d)

Kaleen - Diamantina Crescent

e)

Kambah – Kingsmill Street.

(5) 2016 - Fix My Street Requests

Request for path maintenance

Request for new and upgrade of paths

2200

226