Page 3290 - Week 10 - Thursday, 17 September 2015
Next page . . . . Previous page . . . . Speeches . . . . Contents . . . . Debates(HTML) . . . . PDF . . . . Video
- the University of Canberra Public - Car park for 400 spaces has no explicit expense appropriation for 2015-16 and 2016-17, reference 2015 16 BP3, Page 122. The project has specific appropriation for expenses from 2017-18 but because of the commercially sensitive nature of the project these are Not For Publication (NFP) in the 2015 16 Budget; and
- the University of Canberra Public Hospital has been funded $12.252 million in previous budgets for specification and design of the new hospital, reference 2014-15 BP3, page 138.
Transport—light rail
(Question No 491)
Mr Smyth asked the Treasurer, upon notice, on 12 August 2015:
In relation to the capital contribution for light rail in Budget Paper 3, is the $375 million stated in page 166 included in the $1.5 billion capital provision shown in Table 5.1.1; if so, in which year, or spread of years is it included or if not included in the current Forward Estimates, in which years will it be included.
Mr Barr: The answer to the member’s question is as follows:
The full estimated capital value of the Capital Metro project is included in the $1.5 billion capital provision, apportioned across the years 2016-17 to 2018-19.
The $375 million contribution to the Capital Metro Project represents around half the estimated capital delivery cost of the project. As such, any contribution is implicitly reflected in the capital provision shown in Table 5.1.1.
Finance—government loans
(Question No 492)
Mr Smyth asked the Treasurer, upon notice, on 12 August 2015:
(1) In relation to borrowings and principal outstanding in Budget Paper 3, and the figures underlying the GGS Principal Outstanding for each year, will he provide the (a) opening balance, (b) new borrowings (and expected/intended purpose), (c) repayments/settlements and (d) net principal outstanding (as shown for each year in Table 8.3.2).
(2) What are the interest rates/yield rates payable (or expected to be paid) on these borrowings.
Mr Barr: The answer to the member’s question is as follows:
The information requested is detailed in the attachment.
(A copy of the attachment is available at the Chamber Support Office).
Next page . . . . Previous page . . . . Speeches . . . . Contents . . . . Debates(HTML) . . . . PDF . . . . Video