Page 1919 - Week 06 - Thursday, 5 June 2014

Previous page . . . . Speeches . . . . Contents . . . . Debates(HTML) . . . . PDF . . . . Video


Contract #

Contract

Amount ($)

Directorate

Execution Date

Expiry Date

Status

2013.21048.110

Horse Park Drive Extension - Burramarra Avenue to Mirrabei Drive

9,007,966.66

Economic Development Directorate

26/02/2013

31/10/2015

Work has re-commenced on site. Anticipated completion in accordance with the costs and program laid out in the budget

2012.19125.338

Horse Park Drive Extension to Moncrieff Group Centre

16,903,438.27

Economic Development Directorate

03/07/2012

15/04/2015

Work has re-commenced on site. Anticipated completion in accordance with the costs and program laid out in the budget

2011.15244.320

Molonglo Infrastructure - - Cotter Road / Kirkpatrick Street Intersection Reconstruction

9,072,600.03

Economic Development Directorate

20/10/2011

25/07/2013

Completed and in Defects Liability Period

2012.20891.310

Exhibition Park in Canberra (EPIC) Summernats Burn-Out Track Extension

300,703.70

Territory & Municipal Services Directorate

31/10/2012

14/12/2014

Completed

2013.21704.110.05

Panel of Civil Contractors

0

Economic Development Directorate

09/05/2013

13/05/2014

Panel deed terminated on 13 May 2014

2012.18038.320

Sutton Road Pavement Rehabilitation – Separable Portion 1

2,108,002.54

Territory & Municipal Services Directorate

04/04/2012

01/07/2013

Completed and in Defects Liability Period

2010/13215.320

Kings Highway Southern Deviation

13,895,312.52

Territory & Municipal Services Directorate

22/12/2010

18/04/2013

Completed and in Defects Liability Period

2010.11643.430

Molonglo Infrastructure Stage 1A (Molonglo North South Arterial Part 1 and North Weston Pond)

38,250,934.43

Territory & Municipal Services Directorate

21/01/2010

05/09/2012

Completed and in Defects Liability Period


Previous page . . . . Speeches . . . . Contents . . . . Debates(HTML) . . . . PDF . . . . Video