Page 3548 - Week 11 - Thursday, 19 September 2013
Next page . . . . Previous page . . . . Speeches . . . . Contents . . . . Debates(HTML) . . . . PDF . . . . Video
Daily Average Boardings by Direction and Route | ||||||
Route and Direction |
AM Peak |
Day Off Peak |
PM Peak |
Evening Off Peak |
Daily Average | |
Route 82* | ||||||
City to Bimberi |
- |
3 |
- |
- |
3 | |
Bimberi to City |
- |
- |
7 |
- |
7 | |
Route 200 | ||||||
DFO to Gungahlin |
231 |
931 |
342 |
140 |
1644 | |
Gungahlin to DFO |
751 |
952 |
170 |
83 |
1956 | |
Total Daily Average Boardings |
4,718 |
7,927 |
2,785 |
1681 |
17,111 |
*The Route 50 provides a supplementary service to cater for demand once Route 200 ceases after 7pm.
*The Route 82 operates services in line with the visiting hours of the Bimberi Youth Justice Centre only.
AM Peak = trips commencing from the start of the day to 8:59am
Day Off Peak = trips commencing from 9:00am to 4:29pm
PM Peak = trips commencing from 4:30pm to 5:59pm
Evening Off Peak = trips commencing from 6:00pm until the last service
Water—projects costs
(Question No 143)
Mr Coe asked the Treasurer, upon notice, on 15 August 2013:
(1) What was the (a) agreed Target Outturn Cost (TOC), (b) date of TOC, (c) Actual Outturn Cost (AOC), (d) Gainshare/Painshare amounts broken down by Non Owner Partner fee, adjustment and residential feel and (e) date of commencement and completion of the (i) Murrumbidgee to Googong Transfer (M2G), (ii) Googong Dam Spillway rectification works (GDS), (iii) Tantangara Transfer water licenses (TT), (iv) Murrumbidgee to Cotter augmentation (M2C) and (v) Cotter Pump Station Suction and Discharge Main Upgrade (SD) projects.
(2) What was the (a) original budgeted cost for the projects and (b) final cost, in the event that TOC, AOC, and Gainshare/Painshare amounts are not relevant for any of the projects listed in part (1).
Mr Barr: The answer to the member’s question is as follows:
ACTEW has provided the following table in reply:
Water Security Major Projects (WSMP) — Project Performance
Googong Dam Spillway rectification works (GDS) |
Murrumbidgee to Googong transfer (M2G) |
Tantangara Water licences (TT) |
Murrumbidgee to Cotter augmentation (M2C) |
Cotter Pump Station Suction and discharge Main upgrade (SD) | |
Date of commencement |
30 April 2008 |
27 March 2008 |
1 April 2008 |
30 June 2008 |
30 November 2009 |
TOC Approval date |
24 November 2008 |
25 May 2009 |
N/A |
27 January 2009 |
17 December 2009 |
Target Outturn Cost (TOC) ($m) |
42.3 |
103.9 |
N/A |
17.0 |
18.3 |
Actual Outturn Cost (AOC) ($m) |
40.5 |
76.5 |
N/A |
15.2 |
13.3 |
Next page . . . . Previous page . . . . Speeches . . . . Contents . . . . Debates(HTML) . . . . PDF . . . . Video