Page 3548 - Week 11 - Thursday, 19 September 2013

Next page . . . . Previous page . . . . Speeches . . . . Contents . . . . Debates(HTML) . . . . PDF . . . . Video


Daily Average Boardings by Direction and Route

Route and Direction

AM Peak

Day

Off Peak

PM Peak

Evening

Off Peak

Daily Average

Route 82*

City to Bimberi

-

3

-

-

3

Bimberi to City

-

-

7

-

7

Route 200

DFO to Gungahlin

231

931

342

140

1644

Gungahlin to DFO

751

952

170

83

1956

Total Daily Average Boardings

4,718

7,927

2,785

1681

17,111

*The Route 50 provides a supplementary service to cater for demand once Route 200 ceases after 7pm.

*The Route 82 operates services in line with the visiting hours of the Bimberi Youth Justice Centre only.

AM Peak = trips commencing from the start of the day to 8:59am

Day Off Peak = trips commencing from 9:00am to 4:29pm

PM Peak = trips commencing from 4:30pm to 5:59pm

Evening Off Peak = trips commencing from 6:00pm until the last service

Water—projects costs
(Question No 143)

Mr Coe asked the Treasurer, upon notice, on 15 August 2013:

(1) What was the (a) agreed Target Outturn Cost (TOC), (b) date of TOC, (c) Actual Outturn Cost (AOC), (d) Gainshare/Painshare amounts broken down by Non Owner Partner fee, adjustment and residential feel and (e) date of commencement and completion of the (i) Murrumbidgee to Googong Transfer (M2G), (ii) Googong Dam Spillway rectification works (GDS), (iii) Tantangara Transfer water licenses (TT), (iv) Murrumbidgee to Cotter augmentation (M2C) and (v) Cotter Pump Station Suction and Discharge Main Upgrade (SD) projects.

(2) What was the (a) original budgeted cost for the projects and (b) final cost, in the event that TOC, AOC, and Gainshare/Painshare amounts are not relevant for any of the projects listed in part (1).

Mr Barr: The answer to the member’s question is as follows:

ACTEW has provided the following table in reply:

Water Security Major Projects (WSMP) — Project Performance

Googong Dam Spillway rectification works (GDS)

Murrumbidgee to Googong transfer (M2G)

Tantangara Water licences (TT)

Murrumbidgee to Cotter augmentation (M2C)

Cotter Pump Station Suction and discharge Main upgrade (SD)

Date of commencement

30 April 2008

27 March 2008

1 April 2008

30 June 2008

30 November 2009

TOC Approval date

24 November 2008

25 May 2009

N/A

27 January 2009

17 December 2009

Target Outturn Cost (TOC) ($m)

42.3

103.9

N/A

17.0

18.3

Actual Outturn Cost (AOC) ($m)

40.5

76.5

N/A

15.2

13.3