Forecast based on May 2013 ECD Cost Statement $m |
Pre Target Outturn Cost (TOC) |
37 |
ECD Construction inclusive of NOP Fees |
342 |
Fish Studies & Habitat |
6 |
Cotter Precinct |
9 |
Quality Pool |
3 |
Owner's Costs |
7 |
Net Impact of Flood (net of insurance refund) |
5 |
Total |
409 |
(b) Target Outturn Cost (TOC)
The TOC estimate for the construction of the Cotter Dam as agreed in August 2009 was $263.4 million, with a NOP fee of $35.6 million, giving a total of $299 million. The total project cost estimate including pre TOC costs, Fish Studies and Habitat, Quality Pool and Owner’s Costs - was $363 million. The table below provides a breakdown of these estimates.
Item |
TOC Budget $m |
Pre TOC |
37 |
ECD Construction inclusive of NOP Fees |
299 |
Fish Studies & Habitat |
5 |
Cotter Precinct |
8 |
Quality Pool |
4 |
Owner's Costs |
10 |
Net Impact of Flood |
0 |
Total |
363 |
(c) Gainshare / Painshare amounts
Under the Bulk Water Alliance (BWA) Program Alliance Agreement (PAA) the NOP fees for the Enlarged Cotter Dam are subject to Gainshare/Painshare under the financial model agreed at the time of signing the TOC. The table below shows a summary of the TOC fee versus estimated position of ‘Painshare’ at the end of the project. Painshare/Gainshare may be impacted by the resolution of the insurance claims for flood.
Fee |
TOC Agreed NOP Fee $m |
Estimated NOP Fee at Project Completion $m |
TOC Agreed NOP Fee |
35.6 |
35.6 |
(Pain)/Gain adjustment to NOP Fee |
29.2 | |
Residual Fee |
6.4 |