The following table provides detail on the projects / initiatives currently being delivered.
Site |
Project |
Estimated Cost (excl GST) |
Estimated reduction in energy usage |
Ainslie Fire Station (1) |
Inverter for installation of solar panels, structural engineer / building certifier costs |
$56,000 |
25% Estimated payback of 6 years |
Ainslie Fire Station |
Integrated lighting control System |
$29,500 |
30% Estimated payback 5.6 years |
Alexander Maconochie Centre |
Electrical and lighting consultant – provision of technical advice and scope of works in accordance with energy audit report. |
$8,000 |
Technical advice |
Alexander Maconochie Centre |
Lighting control system upgrade |
$74,800 |
30 to 50% to modified areas |
255 Canberra Avenue (2) |
LED Lighting Upgrade - Joint project with Territory and Municipal Services Directorate (TAMS). |
$17,000 |
55% |
Magistrates Court |
Installation of solar window insulation film. |
$3,000 |
Seasonal change energy savings generated by heat reduction / heat retention, glare reduction and 99% UV Protection |
Magistrates Court |
LED lighting upgrades |
$23,500 |
70% to modified areas |
Magistrates Court |
Chambers 7 & 8 T5 Lighting upgrade |
$5,200 |
40% to modified areas |
12 Moore Street |
Installation of lighting sensors |
$3,000 |
30% to modified areas |
1. Ainslie Fire Station Solar Panels – continuation of work commenced 2011-2012
2. 255 Canberra Avenue – continuation of work commenced 2011-2012
Environment and Sustainable Development Directorate—energy usage
(Question No 35)
Mr Seselja asked the Minister for the Environment and Sustainable Development, upon notice, on 29 November 2012:
(1) What projects or initiatives does the Directorate have planned in the 2012-13 financial year to reduce energy usage.
(2) What is the cost associated with each project or initiative.
(3) What is the estimated reduction in energy usage as a result of the project or initiative.
Next page . . . . Previous page . . . . Speeches . . . . Contents . . . . Debates(HTML) . . . . PDF . . . . Video