(1) It is anticipated that the following funding will be provided for the Canberra Hospital Walk-in Centre, assuming that indexation of salaries and wages (S&W) for nursing staff increases by 3.5% p.a. and indexation of S&W for Administration staff and the operating expenses budget increases by 2.5% p.a. over the four year period.
2012-13 – $2.281m
2013-14 – $2.354m
2014-15 – $2.430m
2015-16 – $2.508m
(2)
(a) Commonwealth
2012-13 – $2.281m
2013-14 – $1.145m
2014-15 – $0.000m
2015-16 – $0.000m
(b) ACT Government
2012-13 – $0.000m
2013-14 – $1.209m
2014-15 – $2.430m
2015-16 – $2.508m
ACT Health—projects
(Question No 2420)
Mr Hanson asked the Minister for Health, upon notice, on 7 June 2012:
What is the scheduled construction start date, scheduled completion date and estimated total cost for the (a) Adult Secure Mental Health Unit, (b) Enhanced Community Health Centre Backup Power, (c) Replacement of Computer Tomography Scanner at The Canberra Hospital, (d) Additional Air Quality Performance Station, (e) Clinical Services Redevelopment (i) Phase 1, (ii) Phase 2 and (iii) Phase 3, (f) Integrated Cancer Care Centre, (i) Phase 1, (ii) Phase 2 and (iii) Phase 3, (g) Central Sterilising Service, (h) Northside Hospital Specification and Documentation, (i) Tuggeranong Health Centre (i) Stage 1 and (ii) Stage 2, (j) Enhanced Community Health Centre – Belconnen, (k) Mental Health Young Persons Unit, (l) New Gungahlin Health Centre, (m) Women and Children’s Hospital, (n) Digital Mammography, (o) Linear Accelerator Procurement, (p) Neonatal Intensive Care Unit – Video Streaming Services and (q) Aboriginal and Torres Strait Islander Residential Alcohol and Other Drug Rehabilitation Facility.
Ms Gallagher: I am advised that the answer to the member’s question is as follows:
a) In relation to the Adult Secure Mental Health Unit, the estimated total cost for finalising design is $3.2m. An estimated scheduled construction start date and completion date cannot be advised as the project is currently in the forward design phase with final design due for completion June 2013. Subsequent to the finalisation of the design, a proposed scope will be developed which will inform the project construction schedule and future Business Case.