Fyshwick Cache Store upgrade

approx. $28k

ACT Ambulance – Calwell and Woden air conditioning upgrades

approx. $8k

Fairbairn HQ – Communication Centre Upgrade

approx. $40k

2. There are no additional works planned for the remainder of 2011-2012.

Community Services Directorate—accommodation
(Question No 2413)

Mrs Dunne asked the Minister for Community Services, upon notice, on 6 June 2012:

(1) Can the Minister provide a list and the corresponding cost of fit-outs, of refurbishments and minor capital works that have taken place in 2011-12 in relation to the Directorate’s accommodation.

(2) What is the scope and cost of any additional accommodation works planned for the remainder of 2011-12.

Ms Burch: The answer to the member’s question is as follows:

(1) In relation to the Directorate’s accommodation, although no minor capital works were completed in 2011-12, the following refurbishment works were completed under the usual repairs and maintenance activity:

o 11 Moore Street, Canberra - 4 additional work stations were installed utilising recycled furniture at a cost of $5000 and a further $4000 to provide additional power and data cabling;

o Nature Conservation House at 153 Emu Bank, Belconnen - In the space vacated by Gateway Services, 6 additional meeting rooms, an IT training room, a kitchen and public toilets have been built at a cost of $710,890;

o Corner of Weingarth St & Blackwood Terrace, Holder - Therapy ACT have had installed 14 additional work stations. All furniture was recycled at a total cost for installation of approximately $2000.

(2) No additional accommodation works are planned for the remainder of 2011-12.

Sport and recreation—ovals
(Question No 2414)

Mr Doszpot asked the Minister for Economic Development, upon notice, on 7 June 2012 (redirected to the Minister for Tourism, Sport and Recreation):

What is the estimated revenue to be received from sportsground and oval fees in each year from 2012-13 to 2015-16.

Mr Barr: The answer to the member’s question is as follows: