Page 370 - Week 01 - Thursday, 17 February 2011
Next page . . . . Previous page . . . . Speeches . . . . Contents . . . . Debates(HTML) . . . . PDF . . . . Video
Functional Brief Lodged |
Call Tenders |
Consultant Engaged |
PSP/Draft Report Completed |
Final design/ Final report Completed |
DA Lodged | |
Woden Valley - Stormwater Retardation Basins |
Yes |
Yes |
Yes |
No |
No |
NA |
Symonston - Arterial Road |
Yes |
Yes |
No |
No |
No |
NA |
(c) All milestones at 31 December 2010 have been met on time with the exception of:
i) Lawson South - Relocation of Power Line Forward Design: Tendering process was delayed.
ii) Molonglo - Future Stormwater Management Feasibility Study: This project is progressing but will be subject to Government decision on options.
iii) Molonglo - East - West Arterial Road and Extension of John Gorton Drive to Molonglo River Feasibility Study: This project cannot commence until the completion of the Molonglo Strategic Assessment and the Planning and Design Framework that are currently underway.
iv) Scrivener Dam Upgrade Feasibility Study: This project has been put on hold pending a decision on the dam upgrade requirement.
(d) Seven staff have been employed, to facilitate the implementation of this program, in addition to a range of other responsibilities.
(e) There is no construction component in the ACTPLA program. Employment of design and study consultants is as per the responses to 1 (a) and (b) above.
(f) As per response to 1 (b) above.
(g) A summary table outlining the completion date of the feasibility studies is shown in Table 2 below. The feasibility study reports will not be publicly released.
Table 2
ACT Planning and Land Authority’s 2010-2011 Feasibility Study Completion Dates
Feasibility Study | |
Completion Date | |
New Capital Works | |
Feasibility Study | |
Molonglo - Future Stormwater Management |
December 2011 |
Molonglo - East-West Arterial Road and Extension of John Gorton Drive to Molonglo River |
October 2011 |
Gungahlin - Town Centre Roads |
June 2011 |
Scrivener Dam Upgrade |
NA |
Woden Valley - Stormwater Retardation Basins |
September 2011 |
Symonston - Arterial Road |
March 2012 |