Functional Brief Lodged

Call Tenders

Consultant Engaged

PSP/Draft Report Completed

Final design/

Final report Completed

DA Lodged

Woden Valley - Stormwater Retardation Basins

Yes

Yes

Yes

No

No

NA

Symonston - Arterial Road

Yes

Yes

No

No

No

NA

(c) All milestones at 31 December 2010 have been met on time with the exception of:

i) Lawson South - Relocation of Power Line Forward Design: Tendering process was delayed.

ii) Molonglo - Future Stormwater Management Feasibility Study: This project is progressing but will be subject to Government decision on options.

iii) Molonglo - East - West Arterial Road and Extension of John Gorton Drive to Molonglo River Feasibility Study: This project cannot commence until the completion of the Molonglo Strategic Assessment and the Planning and Design Framework that are currently underway.

iv) Scrivener Dam Upgrade Feasibility Study: This project has been put on hold pending a decision on the dam upgrade requirement.

(d) Seven staff have been employed, to facilitate the implementation of this program, in addition to a range of other responsibilities.

(e) There is no construction component in the ACTPLA program. Employment of design and study consultants is as per the responses to 1 (a) and (b) above.

(f) As per response to 1 (b) above.

(g) A summary table outlining the completion date of the feasibility studies is shown in Table 2 below. The feasibility study reports will not be publicly released.

Table 2

ACT Planning and Land Authority’s 2010-2011 Feasibility Study Completion Dates

Feasibility Study

Completion Date

New Capital Works

Feasibility Study

Molonglo - Future Stormwater Management

December 2011

Molonglo - East-West Arterial Road and Extension of John Gorton Drive to Molonglo River

October 2011

Gungahlin - Town Centre Roads

June 2011

Scrivener Dam Upgrade

NA

Woden Valley - Stormwater Retardation Basins

September 2011

Symonston - Arterial Road

March 2012