Page 2023 - Week 05 - Thursday, 6 May 2010

Next page . . . . Previous page . . . . Speeches . . . . Contents . . . . Debates(HTML) . . . . PDF . . . . Video


(1)

(a)

(b)

(c)

Body No.

ACTION Delivery date

ACTION Acceptance date

ACTION Acceptance

ACTM001

14-Feb-10

19-Mar-10

Passed

ACTS002

20-Mar-10

30-Mar-10

Passed

ACTS003

26-Mar-10

13-Apr-10

(2) 23.7% of the contract price has been paid to date.

(3) The projected delivery date is dependant on the production capability of the Adelaide Bus Factory of Custom Coaches and the Scania Pre Delivery facility. The expected dates are as indicated in the table below.

Body No.

Projected Delivery date to ACTION

Projected Acceptance date by ACTION

ACTS004

09-Apr-10

22-Apr-10

ACTS005

18-Apr-10

02-May-10

ACTS006

24-Apr-10

08-May-10

ACTS007

24-May-10

07-Jun-10

ACTS008

03-Jun-10

17-Jun-10

ACTS009

12-Sep-10

26-Sep-10

ACTS010

03-Oct-10

17-Oct-10

ACTS011

03-Nov-10

17-Nov-10

ACTS012

22-Nov-10

06-Dec-10

ACTS013

24-Dec-10

07-Jan-11

ACTS014

01-Mar-11

15-Mar-11

ACTS015

25-Apr-11

09-May-11

ACTS016

01-Jun-11

15-Jun-11

ACTS017

24-Jul-11

07-Aug-11

ACTS018

20-Aug-11

03-Sep-11

ACTS019

24-Sep-11

08-Oct-11

ACTS020

22-Oct-11

05-Nov-11

ACTS021

27-Nov-11

11-Dec-11

ACTS022

24-Dec-11

07-Jan-12

ACTS023

28-Jan-12

11-Feb-12

ACTS024

25-Feb-12

10-Mar-12

ACTS025

25-Mar-12

08-Apr-12

ACTS026

22-Apr-12

06-May-12

(4) Excluding GST

$3.125 Million has been paid to the supplier with a further $10.063 Million outstanding

(5) a) ACTS001 was launched on March 16th this vehicle being the first of the series will be utilised over the next 3 weeks by the ACTION Driver Training Section to familiarise ACTION Drivers with this new vehicle type. ACTS001 is projected to enter passenger services on Tuesday April 27th 2010.


Next page . . . . Previous page . . . . Speeches . . . . Contents . . . . Debates(HTML) . . . . PDF . . . . Video