(2) For those items referred to in part (1), how many or what length were installed.
Mr Stanhope: The answer to the member’s question is as follows:
(1) (a) Installation:
i |
Bus shelters |
Approximately $20,000 each (including site works). Adshel shelters are installed at zero cost to the ACT Government |
ii |
Bus seats |
Approximately $1,750 each |
iii |
Buses |
$0.495m (standard), $0.520m (steer tag) and $0.810m (articulated) including all infrastructure required to operate the bus as part of the network (radio and ticketing infrastructure and bike racks). In 2008-09 $7,987,441 was spent on new buses. |
iv |
Roads |
$1.0 million - $20.0 million per km depending on standard of road provided |
v |
Footpaths |
Average cost is $160 per lineal metre |
vi |
Bike paths (off-road shared use paths) new – based upon Mouat St estimate |
$150 – 250/m2 depending upon amount of earthworks, services relocations, drainage, and lighting |
Cycle lanes (on-road) retrofit – based upon State Circle (extensive widening) and Launceston St (minimal widening) |
$130 – 300/m2 depending upon amount of pavement widening required, services to be altered/relocated; light columns to be relocated; extent of line marking adjustments; amount of green pavement treatment | |
vii |
Street lights, by each different type |
Minor pedestrian roads, including cable - $5,000 per street light Major roads, including cable - $7,500 per street light |
viii |
Signs Guide signs (depends on size) |
$150 -200 $200 per m square |
ix |
Linemarking | |
Paints |
$ 20 per m square | |
Long-life material |
$ 110 per m square | |
Green Pavement marking of Bike path |
$ 100 per m square | |
x |
Parking Machines |
$12000 |
xi |
Parking Meters |
$1500 |
xii |
Roundabouts Three-leg Single lane Roundabout Three-leg two -lane Roundabout |
$ 870,000 typically $ 1,600,000 typically |
xiii |
Traffic lights |
About $ 700,000 - $3.5 million depending on situation |
1 (b) Annual Maintenance
i |
Bus shelters |
$44,482 (2008-09) |
ii |
Bus seats |
$7,127 (2008-09) |
iii |
Buses |
$13,523,459 (2008-09) |
iv |
Roads |
$10.7 million |
v & vi |
Footpaths and bike paths |
Community path is made up of $3.0 million from recurrent budget and $2.6 million from cycle path initiative funding |
vii |
Street lights, by each different type |
$4,846,000 (2008-09) |