being developed over the course of the project and will involve subcontracts. The number of and quantum of contracts is yet to be determined as the program is ongoing at this stage.

(4) ACTEW advises that tendering processes used for BWA procurement programs will be in accordance with guidelines set out in the Procurement Management Plan. The table below sets out the standard forms of contracts by which the BWA will engage all suppliers/subcontractors/consultants.

Contract Type

Guidelines for Use

Purchase Order

For minor supply only and “off the shelf” items

Not to be used to engage a consultant

Not to be used to labour

Not to be used where on-site work is involved other than delivery

Not to be used to engage a subcontractor

Supply Agreement

Used for major materials, e.g, concrete, reo, quarry products etc in large quantities rather than a Purchase Order

Used for super critical components of machinery etc irrespective of dollar value

Used for materials requiring commissioning, warranties, completion documentation, manuals etc

Used where the supplier has a design liability or design component

Not to be used where on-site work is involved, other than delivery, without amendment to include site specific special conditions covering safety, environment and Industrial Relations

Plant Hire Agreement

To be used for the hire of external plant

No monetary limits apply

To be tailored to suit whether equipment is on “Dry Hire” where the Alliance takes the risk of damage to and caused by the plant and “Wet Hire” where the risk of damage to the plant and works rests with the Hirer and not the Alliance.

The ‘Letting Approval’ is to include the forecast final cost and the budget details (ie, not merely the hourly rate).

Short Form Subcontract Agreement

A risk assessment of the scope of the work, its complexity and time constraints to be made

Standard Works Subcontract Agreement

A risk assessment of the scope of the work, its complexity and time constraints to be made

Requires tailoring to PAA conditions where applicable

AS4903-based for piling works

Short Form Consultant Services Agreement

No monetary limit but for low value or low risk services

For delivery of routine professional services, eg Flora & Fauna, Heritage, Soil Conservation, Routine Testing, Quality Auditors etc

A risk assessment of the scope of works must be made

Also used for consultants providing reports only without design component

Standard Consultant Services Agreement

To be used in circumstances of medium to high risk where the project is relying upon the professional and expert advice or data provided by a consultant such as a Marine Design Consultant

(5) ACTEW advises that the BWA is committed to taking full advantage of the capabilities of ACT and local NSW industry and, where possible, increasing local content in the Alliance program. The BWA has developed, as part of the Procurement