Hughes

Additional mowing in open space areas, mowing complete, monitoring for further mowing requirements until the end of the fire season.

Complete

Hume

Additional mowing along Monaro Highway, mowing complete, monitoring for further mowing requirements until the end of the fire season.

Complete

Isaacs

Physical removal of fuel hazards within suburb and on Isaacs Ridge

Complete

Isabella Plains

Additional mowing along Isabella Drive, mowing complete, monitoring for further mowing requirements until the end of the fire season.

Complete

Kowen Escarpment

Upgrade of fire trails for plantation protection

Complete

Latham

Additional mowing at rear of houses along Ginninderra Drive and physical removal of fuel hazards obstructing power lines or access at Umbagong Park near Florey Drive and Ginninderra Creek. Mowing complete, monitoring for further mowing requirements until the end of the fire season.

Complete

Macgregor (Mount Goodwin and suburb surrounds)

Physical removal of fuel hazards; improvements to access; additional mowing. Mowing complete, monitoring for further mowing requirements until the end of the fire season.

Complete

Mawson

Additional mowing along Yamba Drive. Mowing complete, monitoring for further mowing requirements until the end of the fire season.

Complete

Monash

Physical removal of fuel hazards and improvements to access. Plantation will also be thinned, lower branches removed. Work on trails will also take place.

Complete

Mount Ainslie

Physical removal of fuel hazards surrounding the ActewAGL substation

Complete

Mount Painter

Additional mowing and grazing of grasslands to the south of the reserve adjacent to William Hovell Drive. Mowing complete, monitoring for further mowing requirements until the end of the fire season.

Complete

Mount Rogers – Fraser

Additional mowing where possible within the reserve and creation of additional fire breaks. Mowing complete, monitoring for further mowing requirements until the end of the fire season.

Complete

Mount Stranger - Bonython

Creation of further access trails to facilitate additional mowing.

Complete

Mount Pleasant (North)

Physical removal of fuel hazards and removal of exotic trees (primarily Radiata and other conifers)

Complete

Ngunnawal Hill

Additional mowing where possible within the reserve. Mowing complete, monitoring for further mowing requirements until the end of the fire season.

Complete

Oakey Hill

Physical removal of fuel hazards and thinning of Bluegum plantations; and creation of fire suppression trails and walking tracks on Oakey East

Complete

O'Connor

Physical removal of fuel hazards in the area between Barry Drive and Dryandra Street

Complete

Oxley Hill

Physical removal of fuel hazards and improvements to access trails

Complete