Megalo Access Arts Centre
(Question No 1190)

Mr Stefaniak asked the Minister for Arts and Heritage, upon notice:

In relation to the relocations of Megalo Access Arts Centre:

(1) What is the status of this project;

(2) What works are planned with the outstanding authorization of

$226 000 for this project;

(3) This project was scheduled for completion in September 2003 was this completion date met. If not, why not.

Mr Wood: The answer to the member’s questions is as follows:

(1) The project is completed.

(2) The budget has been fully expended.

(3) The Minister for Arts and Heritage Mr Bill Wood MLA formally opened the new premises on 5 November 2003.

Manuka Arts Centre
(Question No 1191)

Mr Stefaniak asked the Minister for Arts and Heritage, upon notice

In relation to Manuka Arts Centre:

(1) What is the status of this project;

(2) Is the government still committed to this project;

(3) What works are planned with the outstanding authorisation of $226 000 for this project;

(4) What works have taken place with the $24,000 already expended;

(5) This project is scheduled for completion (as printed in the September 2003 quarterly capital works progress report) in February 2004 will this completion date be met;

(6) If no to (5) why not and what is the new completion date.

Mr Wood: The answer to the member’s questions is as follows:

(1) The project is at preliminary design.

(2) Yes. The Government is committed to the project.