Cotter Road
(Question No 188)
Mr Humphries asked the Treasurer, upon notice, on 4 June 2002:
In relation to the 2001-02 Budget commitment of a further $2.4 million to be spent on Cotter Road, between the Tuggeranong Parkway and Streeton Drive during 2001-02:
(1) What expenditure has been incurred on this capital works project as at 31 March 2002.
(2) What expenditure is expected to be incurred on this capital works project between 31 March 2002 and 30 June 2002.
(3) If the amount committed to this capital works project for 2001-02 is not expected to be spent this financial year, what is the reason for this outcome.
Mr Quinlan: The answer to the member's question is as follows:
(1) Expenditure of $1.111m had been incurred on the Cotter Road (between the Tuggeranong Parkway and Streeton Drive) project to the end of the March quarter 2002. This completes the project.
(2) The scope of the Cotter Road project was revised during 2001-02, and the project value was subsequently reduced to $1.1m
(3) Expected expenditure for the financial year has been fully incurred.
___________________________________________________________________
Drakeford Drive
(Question No 189)
Mr Humphries asked the Treasurer, upon notice, on 4 June 2002:
In relation to the 2001-02 Budget commitment of a further $3.2 million to be spent on Drakeford Drive, between Taverner Street and Erindale Drive during 2001-02:
(1) What expenditure has been incurred on this capital works project as at 31 March 2002.
(2) What expenditure is expected to be incurred on this capital works project between 31 March 2002 and 30 June 2002.
(3) If the amount committed to this capital works project for 2001-02 is not expected to be spent this financial year, what is the reason for this outcome.