(c) $35,750.94

4) Because hard rock and large quantities of ground water were encountered the small CASE bulldozers were unable to cope, necessitating the hire of a larger bulldozer and track . excavator.

(5) (a) Six weeks for the excavation with an estimated cost of - -

$36,-000; -

(b) $64,323.94; -

(c) Two months.

(6) Staff of the ACT Parks and Conservation Service, Department of the Environment, Land and Planning.