1(b)CONSULTANT (2)(a) PURPOSE (2)(b) DURATION (2)(c) COST

31 October 1991

31 March 1992

Purdon & Associates Study of needs of December 1991 - $21,000

elderly Housing Trust June 1992

tenants

Harris van Meegan Evaluation of Housing December 1991 - $4,900

Trust client services June 1992

Harris van Meegan Assistance with staff selection October 1991 $1,825

R Sommerville Assistance with staff selection December 1991 $1,560

Horticultural Landscape Assessment of Aged Persons February - March 1992 $250

Units ground maintenance

Computer Sciences Establish baseline for Bureaus 17 October 1991 - $20,900

Australia information technology 17 February 1992

strategic plan

Ernst and Young Integrated Systems for July 1991 - June 1992 $21,673

(reported previously) Information Processing (ISIP)

Audit

Ernst and Young Audit Off Budget Loans December 1991 - $2,530

(reported previously) Module June 1992